PROJECT 5: CHROME MINING

BEAL (Pty) Ltd has conducted several Engineering services for a Chrome Mining group, such as:

  • CONCEPTUAL ENGINEERING DESIGN (REPORTS, DRAWINGS, AND BOQ)

  • DETAIL ENGINEERING DESIGN (REPORTS, TECHNICAL SPECIFICATIONS, DRAWINGS AND BOQ)

1.

BEAL (Pty) Ltd developed a Conceptual Stormwater management plan to support the water use license application (WULA) for this Chrome Mine.

The Stormwater management plan indicates the sizing and location of the stormwater management infrastructure, such as pollution control dams with spillways, culverts, channels, a leakage detection system and a silt trap.

2.

BEAL (Pty) Ltd reviewed the existing sewage management system and submitted a conceptual design alternative to be approved.

3.

BEAL (Pty) Ltd developed a Detail Sewage Management System, by proposing a separation of grey and black water.

The various sewage management systems utilized throughout the mine include the following:

  • Septic Conservatory tanks

  • French drains

  • Sewage treatment plant

1/2